May 5th, 2023
Published on 5/5/2023
Weekly Update for 05-02-23
It was another busy week at the jobsite. The electrical inspection for the office passed, and we are waiting on the framing inspection before the crews can start the insulation and drywall. All of the partition walls have been completed in Building A and steel will be installed in near future. I personally finished running the network cables for the high-tech surveillance system on the first building. The Findoors are starting to be installed and will be completed this weekend. These trifold doors are very secure, have high R value, keep out pests, and look great. They will be fully powered and will be able to be opened via the keypad or garage door key fob. We will have some demo videos of them in action as soon as they are wired.