Even though we are about 6-8 weeks behind schedule, progress on Building C and D continue.  Due to the impending colder weather Building C and D were built in a different order than previous buildings.  All of the concrete slabs, concrete aprons, concrete curbing, and first layer of asphalt have been laid, so nothing remains on the buildings that is temperature dependent.  Building C will be completed in the next few weeks.  The focus is to have Building C completed first and then finish Building D.  The soffit and metal roof were finished this afternoon.  After the Thanksgiving break, work will continue with installation of the metal exterior walls.  Work continues on Building A as the last of the units are converted to fully insulated and heated units.  Once completed, the entire Building A will be insulated and heated.