Work continues on Building A. The awning was finally installed later this week allowing the electricians to finish pulling the wires for the front of the office. The electricians have been onsite installing the lights, light switches, and outlets. On Friday, the electricians started to power the bay doors. The office flooring will be finished over the weekend and door and trim will come early next week. The construction for the office should be wrapped up in the next 7-10 days, so the storage units can be occupied once the metal walls in each are finished. As each unit is finished, then it will be ready for immediate occupancy.