January 5th, 2024

Published on 1/5/2024
RSS
Construction is getting close to be 100% completed on the whole facility.  The weather so far this winter has been a blessing to keep the construction moving.  Building C is officially open and ready for occupancy.  There are only five 14x40 units remaining with vacancy in building C.  Building D is completed, but we have been waiting on the door motors to be installed before all the electrical work can be finished.  The motors have been stuck in customs for the past few weeks, but hopefully they will be cleared very soon.  We are still in the process of converting the last units in Building A over to fully insulated and heated.  The last 3 heated units will be ready in the next few weeks.