Weekly Update for 05-12-23

It was a quieter on the jobsite this week.  The crews were finishing last framing items in some of the bays and insulation began to be installed in the office and the heated units.  The next three weeks will be extremely busy as we try to get building A ready for rental.  For next week: construction on building B starts, sheetrock will get installed in the office, and metal panels start to be installed in the units.  

Building A is currently full, but we have created a waiting list for heated units that could be available this fall.  Building B and C are filling fast, so don't wait to reserve our spot before they are full.  As of now, we are planning on building A to be ready for rental the first week of June.