Weekly Update for 04-14-23

Not much to report for this weekly update.  The first portion of concrete was poured on Monday.  We are giving it a good week to cure before starting the inside framing.  The summer like weather this week really helped remove much of the frost from the ground.  The crews have been working on the pad for building "B" this week to prepare for the footings and concrete pad that will be coming in the next couple of weeks.

We only have 3 remaining units left in building "A."  The remaining buildings will only be cold storage, so get your fully insulated and heated units before they are sold out.