Weekly Update for 03-31-23

This Winter like weather has really slowed the progress of the build.  We made the decision to bring in heated blankets to thaw the ground instead of waiting for the Spring weather.  A third of the building is currently being thawed to prepare for concrete to be poured the second week of April.  Then we can start framing the office and start finishing the five fully insulated bays.  On the exterior, we are still waiting for the metal awning metal brackets before the remaining of the metal siding is installed.