March 3rd, 2023 Update
Published on 3/3/2023
Weekly Update for Friday 03-03-23
After some weather delays from the previous week, the construction crew has been working hard to get back on schedule. The majority of the external framing has been completed for building "A." The remaining exterior framing for the office and facias will be completed early next week, and then the crews will start installing the metal roof.